Timeline
Subject to
planning*

Autumn 2024
The project is established to deliver much needed housing and community assets for the borough. Work on the vision for Avion Crescent commenced.

Winter 2024
Initial surveys of the site are undertaken and some preliminary concept design work is completed.

Winter
2024 – start 2025
Commencement of more detailed early design proposals to help inform consultation.

Jan/Feb 2025
Public consultation on the plans for the future of the site with the area’s
residents, businesses and stakeholders.

Summer /
Autumn 2025
Ongoing development of the design in response to public consultation, local
planning authority feedback and design team development.

Winter
2025
Prepare planning application including obtaining wider input from a team of
specialist consultants.

February 2026
We’re here: Submission of planning application

Spring /
Summer 2026
Anticipated planning consent.

Summer
2026
Development of detailed design and early packages

Autumn
2026
Site mobilisation/ early construction work begins.*

2028/ 2029
First residents move in.*